3rd Ring Road is scheduled to handover in September 2022

MGO News 05-27

ផ្លូវក្រវ៉ាតក្រុងទី៣នឹងសាងសង់នៅក្នុងពេលឆាប់ៗខាងមុខ


Phnom Penh (MGO) – As of May 25, the 3rd Ring Road construction has reached 73.70% and is scheduled to be completed as planned during September 2022.


According to the Phnom Penh Department of Public Works and Transport, the third ring road is the city ring road from the southwest to the east of Phnom Penh, with a length of 53 km and a width of 22 km. From National Road 4 to National Road 1, a 22 cm thick reinforced concrete road.


The construction of this project was opened in January 2019 and will cost about 273 million US dollars, a loan from China. This 3rd Ring Road has a total length of 52.9 km through Kandal province, nearly 38 km, and Phnom Penh,15 kilometers. 


This road is under construction by Shanghai Construction Group Co., Ltd., and technical inspection of Guangzhou Wanan Construction Supervision Co., Ltd. In addition to the 3rd Ring Road , the government also plans to build the 3rd Ring Road on the east side to create a full ring road.

 

Translator: Leakna 